SBS Panel Square Foot Costs

Scenario #1

Costs for a 16' wide by 24' tall panel (384 square feet) load bearing wall using 6" studs on 16" centers

MATERIALS
ITEM DESCRIPTION UNIT AMT COST TOTAL SF COST
Studs & Track 15/8" x 6" x 16ga on 16" OC 13 @ 24' LF LF 344 $1.80 $619.20 $1.61
Mesh 384 sf + 24 sf for laps SF 408 $0.13 $53.04 $0.14
Cable For lift points 4 ea LF 24 $0.50 $12.00 $0.03
Screws For framing the panel SF 384 $0.04 $15.36 $0.04
Anchors Threadall and epoxy 9 ea EA 9 $3.00 $27.00 $0.07
Bolts Panel bolts & Washers EA 15 $1.00 $15.00 $0.04
Forms Forming Lumber LF 80 $1.25 $100.00 $0.26
Bond Breaker Bond breaker & Cure SF 384 $0.08 $30.72 $0.08
Concrete 3500# 3/8 @ 2" + 5 yd for picks CY 2.87 $65.00 $186.55 $0.49
Patch Sack and Patch Material SF 384 $0.03 $11.52 $0.03
        Total $1,070.39 $2.79

LABOR
ITEM DESCRIPTION UNIT AMT COST TOTAL SF COST
Frame Fabricate 15 pcs - 2 men 3 hour ea HRS 6.6 $30.00 $198.00 $0.52
Form Form 80' LF 2 men 1.5 hour ea HRS 3 $30.00 $90.00 $0.23
Mesh Cut & Tie 384 sf 2 men .75 hour ea HRS 1.5 $30.00 $45.00 $0.12
Picks Install 4 pcs cable 1 man hour HRS 1 $30.00 $30.00 $0.08
Place concrete Pour & float 2.87 cy 4 men 1 hour ea HRS 4 $30.00 $120.00 $0.31
Patch 1 man 2 hour HRS 2 $30.00 $60.00 $0.16
Erect 4 men .5 hour ea HRS 2 $30.00 $60.00 $0.16
Anchors 9 bolts 10 min ea 1.5 hour HRS 1.5 $30.00 $45.00 $0.12
  Total Labor HRS 21.6 TOTALS $648.00 $1.69

EQUIPMENT & SUBS
ITEM DESCRIPTION UNIT AMT COST TOTAL SF COST
Pump Concrete Pump YDS 2.87 $13.00 $37.31 $0.10
Crane $200 Per Hour HRS 0.6 $200.00 $120.00 $0.31
Braces Brace Rent for 24' H $24/Month Each EA 2 $24.00 $48.00 $0.13
Vert Joints Backer Rod and Caulk LF 24 $3.00 $72.00 $0.19
  Total Equipment       $277.31 $0.72

RECAP SF COSTS FOR 16L X 24H PANEL
ITEM DESCRIPTION UNIT AMT COST TOTAL SF COST
Materials         $1,070.39 $2.79
Labor         $648.00 $1.69
Equipment         $277.31 $0.72
Use Fees SBS Royalties       $384.00 $1.00
  Total Panel Cost       $2,379.70 $6.20




Scenario #2

Costs for a 16' wide by 24' tall panel (384 square feet) load bearing wall using 8" studs on 24" centers

MATERIALS
ITEM DESCRIPTION UNIT AMT COST TOTAL SF COST
Studs & Track 15/8" x 8" x 16ga on 24" OC 9 @ 24' LF LF 248 $1.95 $483.60 $1.26
Mesh 384 sf + 24 sf for laps SF 408 $0.13 $53.04 $0.14
Cable For lift points 4 ea LF 24 $0.50 $12.00 $0.03
Screws For framing the panel SF 384 $0.04 $15.36 $0.04
Anchors Threadall and epoxy 9 ea EA 9 $3.00 $27.00 $0.07
Bolts Panel bolts & Washers EA 15 $1.00 $15.00 $0.04
Forms Forming Lumber LF 80 $1.25 $100.00 $0.26
Bond Breaker Bond breaker & Cure SF 384 $0.08 $30.72 $0.08
Concrete 3500# 3/8 @ 2" + 5 yd for picks CY 2.87 $65.00 $186.55 $0.49
Patch Sack and Patch Material SF 384 $0.03 $11.52 $0.03
        Total $934.79 $2.43

LABOR
ITEM DESCRIPTION UNIT AMT COST TOTAL SF COST
Frame Fabricate 11 pcs - 2 men 3 hour ea HRS 6 $30.00 $180.00 $0.47
Form Form 80' LF 2 men 1.5 hour ea HRS 3 $30.00 $90.00 $0.23
Mesh Cut & Tie 384 sf 2 men .75 hour ea HRS 1.5 $30.00 $45.00 $0.12
Picks Install 4 pcs cable 1 man hour HRS 1 $30.00 $30.00 $0.08
Place concrete Pour & float 2.87 cy 4 men 1 hour ea HRS 4 $30.00 $120.00 $0.31
Patch 1 man 2 hour HRS 2 $30.00 $60.00 $0.16
Erect 4 men .5 hour ea HRS 2 $30.00 $60.00 $0.16
Anchors 9 bolts 10 min ea 1.5 hour HRS 1.5 $30.00 $45.00 $0.12
  Total Labor HRS 21 TOTALS $630.00 $1.64

EQUIPMENT & SUBS
ITEM DESCRIPTION UNIT AMT COST TOTAL SF COST
Pump Concrete Pump YDS 2.87 $13.00 $37.31 $0.10
Crane $200 Per Hour HRS 0.6 $200.00 $120.00 $0.31
Braces Brace Rent for 24' H $24/Month Each EA 2 $24.00 $48.00 $0.13
Vert Joints Backer Rod and Caulk LF 24 $3.00 $72.00 $0.19
  Total Equipment       $277.31 $0.72

RECAP SF COSTS FOR 16L X 24H PANEL
ITEM DESCRIPTION UNIT AMT COST TOTAL SF COST
Materials         $934.79 $2.43
Labor         $630.00 $1.64
Equipment         $277.31 $0.72
Use Fees SBS Royalties       $384.00 $1.00
  Total Panel Cost       $2,226.10 $5.80